SODABOB
Well-Known Member
- Joined
- Aug 10, 2016
- Messages
- 2,121
- Reaction score
- 481
- Points
- 83
Now I get to do a little speculating - so bear with me because I'm making this up as I go ...
1. I have to assume when the permit was filed they already had blueprints drawn up. How else would they know how large the slab would be?
2. If they had blueprints of the floor plan, they no doubt knew where the offices, bottling area, warehouse, etc. would be located. Not to mention where the underground utilities such as water lines, drains, etc. would be located. As for the electric and phone connections, that probably came later and were above ground and inside the walls.
3. If they had blueprints of the floor plan, those plans no doubt included the 'tower' part of the building where the 3-1-3 neon sign would be installed.
4. If they knew where the tower and sign were located, they no doubt knew how large of a sign they needed to sit on top of the tower.
5. Which leads me to believe they already knew what size and type of sign they needed/wanted when the concrete slab permit was filed on December 24, 1938.
6. What we don't know is how long it took to design and manufacture the sign - nor if that took place in 1938 or just prior to the time when the building was partially completed in April of 1939. The April 15, 1939 picture I posted earlier shows the sign already installed.
7. A far as how long it took to manufacture the sign goes, the one thing that jumps out at me most is that it was an "electric neon" sign and it probably took a little time and effort to construct it.
8. Regarding whose decision it was to put the 3-1-3 bubbles on the sign, my best guess is that D.K. Washburn (President) likely had the final say in all construction matters regardless of who might have been advising him.
9. Hence, the question as to which came first, the 3-1-3 sign or the 7313 phone number, my best guess is to say ...
"Stay Tuned"
1. I have to assume when the permit was filed they already had blueprints drawn up. How else would they know how large the slab would be?
2. If they had blueprints of the floor plan, they no doubt knew where the offices, bottling area, warehouse, etc. would be located. Not to mention where the underground utilities such as water lines, drains, etc. would be located. As for the electric and phone connections, that probably came later and were above ground and inside the walls.
3. If they had blueprints of the floor plan, those plans no doubt included the 'tower' part of the building where the 3-1-3 neon sign would be installed.
4. If they knew where the tower and sign were located, they no doubt knew how large of a sign they needed to sit on top of the tower.
5. Which leads me to believe they already knew what size and type of sign they needed/wanted when the concrete slab permit was filed on December 24, 1938.
6. What we don't know is how long it took to design and manufacture the sign - nor if that took place in 1938 or just prior to the time when the building was partially completed in April of 1939. The April 15, 1939 picture I posted earlier shows the sign already installed.
7. A far as how long it took to manufacture the sign goes, the one thing that jumps out at me most is that it was an "electric neon" sign and it probably took a little time and effort to construct it.
8. Regarding whose decision it was to put the 3-1-3 bubbles on the sign, my best guess is that D.K. Washburn (President) likely had the final say in all construction matters regardless of who might have been advising him.
9. Hence, the question as to which came first, the 3-1-3 sign or the 7313 phone number, my best guess is to say ...
"Stay Tuned"